II subway line in Warsaw – C16, C17, V16, V17

31 January 2018

On January 31, 2018, Instal-Lublin Sp. z o.o. has received a mutually signed agreement dated January 26, 2018, concluded with Astaldi S.p.A. for the construction of second subway line in Warsaw – first stage of the east-north section from the route after the station C15 “Dworzec Wileński” to the storage tracks behind the C18 station.

The subject of the Agreement is execution, delivery and installation of equipment, commissioning, maintenance and removal of faults – mechanical installations at C16, C17 and track ventilation rooms V16, V17, excluding air-conditioning systems.

According to the schedule attached to the Agreement, the subject of the Contract should be performed by 30/03/2019.