15 June 2016
On 15.06.2016 Mostostal Power Development has commissioned us the work execution in the area of Opole Power Plant.
The contract covers the installation of water and sewerage systems in buildings: 5UEF – coal impact loading tower, 2UEA40 – railcars tippler, 1UEA40 – railcars defrosting, UVF – limestone powder magazine, 5UHX10, 5UHX20, 6UHX10, 6UHX20 – pylons in 5 and 6 units.
The value of contracted work is approximately 1.4 million PLN.
The work will last until 15.03.2017.